City of Prescott Public Works Projects

The City of Prescott issues updates on its public works projects every Friday. Here are the active projects for Monday, April 19 through Friday, April 23. Visit www.prescottutilityimprovements.com for additional project information, or call 928-237-3114. To receive weekly eNews project updates directly from the City of Prescott, email a request to: news@prescottutilityimprovements.com.

MILE HIGH PARK WATER LINE IMPROVEMENTS PROJECT

The City of Prescott and their contractor, Asphalt Paving & Supply, Inc., are currently working on a water line improvement project. The project includes the removal and replacement of the old, undersized water main and services in the areas highlighted below. Additional work includes reconstructing the low-water crossing along Mayo Street and installing new asphalt pavement throughout the project.

Once complete, these improvements will increase water system reliability by upgrading the existing infrastructure for the Mile High Park Neighborhood. The project is scheduled to be complete in spring 2021.

WATER MAIN INSTALLATION ONGOING

Water main installation will continue along Keen Street, south of the Paar Drive intersection, throughout the week.

Please be aware of the following impacts:

Monday, April 19 through Thursday, April 22, 6 a.m. – 6 p.m.
Sections of Keen Street will be closed to through traffic, south of the Paar Drive intersection, during work hours. Follow the marked detour signage to get to your destination. Please be aware of staged equipment, lane restrictions, reduced speeds, rough road conditions, and flagging operations throughout the work zone.

STREET PARKING AND ACCESS

To minimize conflicts with construction equipment, and expedite completion of the project, the City asks that you avoid on-street parking while construction is underway. Personnel will work with residents to maintain driveway access throughout the work zones.

FY20 CONCRETE REPAIRS & DRAINAGE IMPROVEMENTS PROJECT

The City of Prescott and their contractor, Capital Improvements, are currently working on a concrete repair project throughout the City. Improvements include the removal and replacement of concrete sidewalks, curb and gutter, scuppers and roadway striping as needed at various locations throughout the Prescott community. Curb ramp installation, storm drain replacement, brush removal and landscape operations will also take place as part of this project.

Once complete, this project will improve drainage, increase pedestrian safety and extend the life of the repaired concrete into the foreseeable future. The project is schedule for completion in spring 2021.

CONCRETE WORK TO BEGIN ON SANDRETTO DRIVE

Crews will be removing and replacing concrete sidewalks, and curb and gutter along the north side of Sandretto Drive, just west of Aster Drive, throughout the week.

Please be aware of the following impacts:

Monday, April 19 through Friday, April 23, 6 a.m. – 6 p.m.
Please be aware of lane restrictions, reduced speeds, and flagging operations throughout the work zone.

SIDEWALK CLOSURES

Temporary sidewalk closures will be required to perform this work; however, personnel will work to accommodate access for local businesses and residents.